busy summer

Town to spend millions on infrastructure projects this year

May 5, 2026 | 1:26 PM

There are multiple infrastructure projects the Town of La Ronge will be busy with in 2026.  

One of the most expensive projects will include road and sidewalk maintenance and repair. While the entire scope of work is yet to be determined, administration has been in talks with an engineering company to create a plan. 

There is $3.6 million earmarked for the work with the town hoping to receive $856,000 in grant money for it. 

“We need to be realistic on how many repairs we can do in one year,” an email to larongeNOW from the municipality states.  

“We do not yet know exactly which streets will be affected at this point, we do not have an exact amount as to what these repairs will cost, and where and when these repairs will happen. The amount listed in the budget is just an estimate. After the consultation process is complete, we will have a better answer of where and when the repairs will take place.” 

A sewer pipe lining project is also in the capital budget with an estimated cost of $2.9 million. Of that, the town is expected to spend $725,000 in town reserves with the remainder coming from external grant funding. 

“The idea with this is to put a lining inside our sewer pipes in order to alleviate any current issues with the pipes while also increasing the longevity of the sewer pipes,” the email notes.   

“Again, in a similar situation to the road repairs, we do not yet have an exact scope of where this is needed the most and we are working with our engineering company to help out with the planning of this.” 

Other work to be completed include sanitary water and distribution repairs, the creation of a playground and green space along near Robertson Drive, and water curb stop replacements.  

The sanitary water and distribution repairs is still in the planning phase and is expected to cost $1.2 million with $900,000 coming from external funding, while curb stop repairs will cost $58,000 from town reserves.  

“We do know that repairs are needed to this infrastructure (sanitary water and distribution). Once we have consulted with our engineers, we will have a better understanding on the location, scope and dates of this project,” the email added. 

The Robertson Park is expected to cost $330,000 with $100,000 coming from grant money.

— 