HARP solutions found problems ranging from road work to drainage issues. (Image Credit: Derek Cornet/larongeNOW Staff)
upgrades needed

Village working to address issues outlined in recent report

Jul 23, 2026 | 3:25 PM

A report from HARP Solutions Inc. is highlighting a number of issues which need to be addressed in the Village of Air Ronge.  

HARP Solutions representatives conducted weekly public works support site visits of the village’s municipal facilities on June 18 and 19 and June 24 and 25. During the visits, HARP worked alongside staff members, evaluated facility operations for compliance and efficiency, reviewed documentation, advised on systems, and more.  

HARP found a number of issues and outlined them in their report. One of the issues was finding asbestos in the dry pit of a sewage lift station.

“Staff should not be entering without appropriate respiratory protection. The community needs to have this professionally removed as soon as possible.” 

An email to larongeNOW from village administration states council was previously aware of the issue and was already seeking a qualified firm to remediate it.

HARP also found there are a number of curb stops, or underwater control valves, that are bent and need to be fixed so they can operate properly when required. 

The administration responded to this issue by stating mapping, lowering, and repairing curb stops is an ongoing process and will be completed as time allows around the many essential other duties that public works completes. 

HARP noted there is significant deterioration of the pavement in many areas of the community and while some areas are ok, there is a lot of areas that have significant alligator cracking. They recommended a strategic paving upgrade program should be implemented as soon as possible to prevent further damage. 

“Council and staff are assessing the full scope of the village’s paving requirements and expect to address priority areas within upcoming budget planning,” the email stated. 

The report also recommends the village should start planning for improved draining in the Village. It notes the community uses extensive surface draining and that soil and debris buildup in ditches and culverts is extensive. The project will likely include culvert jetting, replacements, ‘shooting in’ and sloping ditches, and soil removal. 

The village has already secured a consultant who is currently upgrading the 2013 drainage plan. Staff have reviewed it and completed field assessments, and the engineering firm is expected to be conducting preliminary onsite surveying this summer. 

Finally, HARP found communication was an issue expressed by multiple parties during the onsite visit. They recommend a structured communication plan should be developed so administration is aware of day-to-day activities, while allowing field staff to get work done.  

The village responded by noting a communication plan is already in place moving to daily in-person meetings, with additional electronic connection and follow up. 